in Management by (3.8k points)
When is the project manager assigned to a project?

(A) After the contract is signed.

(B) Immediately preceding contract execution.

(C) During contract initiation.

(D) During contract planning.

1 Answer

0 votes
by (17.6k points)
 
Best answer

Correct option is (C) During contract initiation.