in Management by (3.8k points)
As a project manager, you are presented with the following information on the NPV for several potential projects. Which project is your best choice?

(A) Project A with a NPV of US $95,000.

(B) Project B with an NPV of US $120,000.

(C) Project C with an NPV of US $20,000.

(D) Project D with an NPV of US $30,000.

1 Answer

0 votes
by (17.6k points)
 
Best answer

Correct option is (B) Project B with an NPV of US $120,000.

...