in Management by (3.8k points)
You are beginning a new project that has been attempted, but unsuccessful, several times in the past few years. Previous projects were cancelled because of "politics," (differing views and direction by key stake holders of the project). This is an example of:

(A) Project charter.

(B) Stakeholder analysis.

(C) Risk identification.

(D) Historical information.

1 Answer

0 votes
by (17.6k points)
 
Best answer

Correct option is (D) Historical information.

You are beginning a new project that has been attempted, but unsuccessful, several times in the past few years. Previous projects were cancelled because of "politics," (differing views and direction by key stake holders of the project). This is an example of Historical information.

...